Concrete Calculator

Ordering short means a cold joint and a second truck; ordering long means paying to dispose of it. The waste allowance is shown separately here so you can see exactly what you are padding by.

The Pour

Thickness in inches, everything else in feet.

ft
ft
Slabs are usually 4 in, driveways 5–6 in
in
in
ft
5–10% is typical for a flat slab
%
CONCRETE NEEDED
Volume before waste
Waste allowance
Cubic feet
Cubic metres
Approximate weight
Order from a truck?

If you are bagging it

60 lb bags (0.45 ft³ each)
80 lb bags (0.60 ft³ each)
Water needed, 80 lb bags
Pallets of 80 lb bags (42/pallet)

Why concrete is ordered in cubic yards

A cubic yard is 27 cubic feet, and a standard ready-mix truck carries 8 to 10 of them. Anything much above a cubic yard is cheaper and far easier from a truck than from bags: one cubic yard is 45 bags of 80 lb mix, which is roughly 1.8 tonnes to carry, mix and place before the first batch starts setting.

The waste allowance is not padding

Subgrade is never perfectly flat, forms bow slightly under pressure, and some concrete is lost in the chute and on the ground. Five per cent is the minimum realistic allowance on a well-prepared flat slab; ten is normal; footings in soft or uneven ground can need more. The figure is shown separately above so you can judge it rather than inherit it.

Thickness matters more than area

Volume scales linearly with thickness, so going from 4 inches to 5 adds 25 per cent to the order — a much bigger jump than most people expect from “just an inch”. It is also the single most common cause of an order coming up short: the slab was priced at 4 inches and poured closer to 5 because the subgrade dipped.

Order by the yard, and order slightly long

Ready-mix is sold by the cubic yard, which is 27 cubic feet, and suppliers normally quote a minimum load plus a short-load surcharge below roughly one cubic yard. Running out mid-pour is far more expensive than a small surplus: a cold joint forms where fresh concrete meets concrete that has already begun to set, and that joint is a permanent weakness. Adding five to ten per cent covers subgrade that is not perfectly level, which is where most of the extra volume quietly goes.

Bagged mix is a different calculation. A 60 lb bag yields about 0.45 cubic feet and an 80 lb bag about 0.60, so a modest 4-inch slab of 80 square feet still needs roughly 45 bags of the larger size. Beyond a cubic yard or so, mixing by hand stops being realistic and ready-mix is both cheaper and more consistent. Control joints should be tooled or cut at roughly 24 to 30 times the slab thickness in feet, which puts a 4-inch slab at 8 to 10 feet.

Frequently Asked Questions

How many bags of concrete are in a cubic yard?
About 45 bags of 80 lb mix or 60 bags of 60 lb mix, since an 80 lb bag yields roughly 0.60 cubic feet and 27 cubic feet make a yard.
How much waste should I allow?
Five per cent on a well-prepared flat slab, ten per cent for typical work, and more for footings in uneven ground. Running short mid-pour is far more costly than a little excess.
When should I order ready-mix instead of bags?
Above about one cubic yard. That is already 45 bags of 80 lb mix — around 1.8 tonnes to move and place within the working time of the first batch.
How much does concrete weigh?
Roughly 4,000 lb per cubic yard, or about 150 lb per cubic foot, for normal-weight mixes.